Prompt Details
Model
Chat - (gpt-5.5)
Token size
969
Example input
[choose one]: Scope of work section
[e.g. Oil & Gas Pipeline / Refinery / Chemical Plant / Power Plant / Water Treatment / Infrastructure / Any]: Oil and gas refinary
[2–5 sentences describing the project — scope, location, approximate value, client type]: Revamp of CDU/VDU unit at Mumbai refinery, ₹45 crore project, IOC as client
[Your company name, location, key strengths to highlight — e.g. "15 years experience, ISO certified, completed 3 similar projects"]: Your company name, ISO certified, 10 years experience
[PREFERENCES]: Tone : Highly Formal+ Client requirements: Standard EPC tender requirements
Example output
1.0 SCOPE OF WORK
1.1 General Overview
ABC Engineering & Projects Pvt. Ltd. (hereinafter referred to as the “Contractor”), an ISO 9001:2015 certified EPC organization with over 10 years of proven experience in refinery and hydrocarbon sector projects, hereby submits its Scope of Work proposal for the Revamp of the Crude Distillation Unit (CDU) and Vacuum Distillation Unit (VDU) at the Indian Oil Corporation Limited Mumbai Refinery.
The proposed revamp works shall be executed on a Lump Sum Turnkey (LSTK) EPC basis and shall include complete Engineering, Procurement, Construction, Testing, Pre-commissioning, and Commissioning assistance for the successful upgrade and integration of the existing refinery process facilities in accordance with the Client’s tender specifications, applicable statutory regulations, and international refinery engineering standards.
The approximate project value is INR 45 Crore.
2.0 PROJECT OBJECTIVE
2.1 Objective of Revamp
The primary objective of the CDU/VDU revamp is to enhance operational efficiency, improve throughput reliability, optimize energy utilization, and ensure compliance with updated refinery safety and operational standards without adversely impacting ongoing refinery operations.
The Contractor shall execute all activities necessary to achieve safe integration with existing operating units while minimizing shutdown duration and operational disruptions.
3.0 ENGINEERING SCOPE
3.1 Detailed Engineering
The Contractor shall perform complete detailed engineering for the revamp works including, but not limited to, the following activities:
Process design validation and revamp assessment
Hydraulic analysis of existing piping systems
Equipment sizing verification and debottlenecking study
Preparation of Process Flow Diagrams (PFDs)
Preparation and updation of Piping & Instrumentation Diagrams (P&IDs)
3D model development and clash analysis
Isometric drawings and piping GA drawings
Pipe stress analysis in accordance with ASME B31.3
Structural adequacy assessment for modified loads
Electrical load study and cable schedule preparation
Instrument loop drawings and control philosophy
Hazardous area classification review
Shutdown planning and tie-in engineering
3.2 Engineering Standards and Codes
All engineering activities shall comply with the latest applicable editions of the following standards and codes:
ASME B31.3 — Process Piping
API 650 — Welded Tanks for Oil Storage
API 610 — Centrifugal Pumps for Petroleum Services
API 570 — Piping Inspection Code
API 653 — Tank Inspection and Repair
IEC Standards for Electrical Systems
NFPA Standards for Fire Protection Systems
OISD Standards applicable to refinery installations
Indian Boiler Regulations (IBR), wherever applicable
ISO 9001:2015 Quality Management Requirements
3.3 Engineering Deliverables
The Contractor shall submit the following key deliverables:
1. Project Execution Schedule – Within 7 Days
2. PFDs & Updated P&IDs – Within 3 Weeks
3. Equipment GA Drawings – Within 4 Weeks
4. IFC Piping Drawings – Within 6 Weeks
5. Electrical & Instrument Drawings – Within 6 Weeks
6. Shutdown & Tie-in Plan – Within 5 Weeks
7. QA/QC Documentation – Prior to Construction
8. As-Built Documentation – Within 30 Days of Mechanical Completion
4.0 PROCUREMENT SCOPE
4.1 Procurement Responsibilities
The Contractor shall be responsible for complete procurement, inspection, expediting, transportation, and delivery of all materials and equipment necessary for execution of the revamp works.
The procurement scope shall include:
Process piping and fittings
Valves and specialty valves
Structural steel materials
Electrical cables and cable trays
Instruments and junction boxes
Pipe supports and accessories
Gaskets, fasteners, and consumables
Insulation and painting materials
4.2 Vendor Inspection
Inspection and testing activities shall be carried out in accordance with approved Inspection & Test Plans (ITPs). Third-party inspection agencies approved by the Client shall be engaged wherever specified in the tender requirements. Material Traceability Records (MTRs) shall be maintained for all critical refinery service materials.
5.0 CONSTRUCTION SCOPE
5.1 Site Construction Activities
The Contractor shall execute all field construction activities including:
Dismantling of identified existing systems
Fabrication and erection of process piping
Equipment erection and alignment
Structural steel erection
Electrical cable laying and termination
Instrument installation and loop checking
Fireproofing, insulation, and painting
Tie-ins during planned shutdown windows
Hydrotesting and reinstatement works
5.2 Construction Methodology
Construction activities shall be executed in accordance with approved Method Statements, Job Safety Analysis (JSA), and refinery permit-to-work procedures.
All hot work activities shall strictly comply with refinery safety protocols and OISD guidelines.
The Contractor shall deploy qualified supervisors, certified welders, safety officers, and QA/QC personnel throughout the execution phase.
5.3 Welding Requirements
All welding activities shall comply with:
ASME Section IX
Approved Welding Procedure Specifications (WPS)
Procedure Qualification Records (PQR)
Welder Qualification Records (WQR)
Minimum 10% radiography shall be carried out for process piping weld joints unless otherwise specified by the Client.
6.0 TESTING AND PRE-COMMISSIONING
6.1 Mechanical Completion Activities
The Contractor shall perform:
Hydrostatic testing
Pneumatic leak testing where applicable
Flushing and cleaning
Air blowing
Calibration of instruments
Loop checking
Functional testing of electrical systems
6.2 Pre-Commissioning Support
The Contractor shall provide commissioning assistance including:
System handover dossiers
Punch point rectification
Trial run support
Operator assistance during startup
Final documentation submission
7.0 HEALTH, SAFETY AND ENVIRONMENT (HSE)
7.1 HSE Compliance
The Contractor shall implement a comprehensive HSE management system compliant with:
OISD refinery safety standards
ISO 45001 Occupational Health & Safety requirements
Applicable environmental regulations of Maharashtra Pollution Control Board (MPCB)
A dedicated HSE team shall be deployed at site for continuous monitoring and compliance enforcement.
7.2 Safety Targets
The Contractor commits to achieving:
Zero Lost Time Injuries (LTI)
Zero major fire incidents
100% toolbox talk compliance
100% PPE adherence at site
8.0 QUALITY ASSURANCE AND QUALITY CONTROL
8.1 Quality Management
All project activities shall be executed under the Contractor’s ISO-certified Quality Management System.
The QA/QC scope shall include:
Material receiving inspection
Welding inspection
NDT coordination
Dimensional verification
Painting and coating inspection
Final mechanical clearance
8.2 Documentation Control
All project documentation shall be maintained through a controlled document management system ensuring revision traceability and timely submission.
9.0 PROJECT SCHEDULE
9.1 Execution Timeline
The Contractor proposes to complete the entire EPC scope within 10 months from the effective date of Letter of Award (LOA), including engineering, procurement, construction, and pre-commissioning support activities.
Critical shutdown activities shall be completed within the refinery shutdown window as finalized jointly with the Client.
10.0 SCOPE EXCLUSIONS
The following activities are excluded from the Contractor’s scope unless specifically included in the final Contract Agreement:
Statutory fees payable directly to government authorities
Long shutdown extensions beyond approved duration
Supply of Client free-issue materials
Major civil foundation modifications not identified in tender documents
Operation and maintenance beyond commissioning support period
Existing underground utility rerouting not indicated in AFC drawings
Process performance guarantee beyond defined tender parameters
11.0 CONTRACTOR’S COMMITMENT
ABC Engineering & Projects Pvt. Ltd. remains committed to executing the CDU/VDU Revamp Project with the highest standards of safety, quality, engineering excellence, and schedule adherence.
The Contractor appreciates the opportunity extended by Indian Oil Corporation Limited and looks forward to establishing a successful long-term professional association through safe and timely project delivery in line with the Client’s operational objectives and refinery standards.
1. SCOPE GAPS — COMMONLY MISSED IN EPC TENDERS
1.Shutdown Interface Planning
Many tenders fail to clearly define tie-in responsibilities, shutdown sequencing, and refinery coordination methodology, leading to lower technical evaluation scores.
2. Construction Constraint Identification
Lack of mention regarding live refinery work restrictions, SIMOPS management, and access limitations weakens execution credibility.
3. Document Submission Schedule
Generic deliverable commitments without specific timelines reduce confidence in engineering preparedness and project controls capability.
2. COMPLIANCE CHECK — VERIFY BEFORE SUBMISSION
Confirmation of compliance with all applicable OISD standards
Inclusion of detailed HSE statistics and safety commitment
Confirmation of validity period of offer and execution schedule
Confirmation of compliance with refinery permit-to-work systems
Inclusion of deviations/clarifications list, even if NIL
3. WINNING EDGE TIP
Include a dedicated “Refinery Shutdown Management Strategy” subsection with manpower histogram, hour-by-hour shutdown execution plan, and tie-in methodology. IOC technical evaluators typically score higher for bidders demonstrating strong shutdown execution capability and operational risk minimization.
4. FOLLOW-UP TEMPLATE
A professional follow-up email is provided below.
Subject : Submission of Technical Proposal – CDU/VDU Revamp Project
Dear Sir/Madam,
We thank you for the opportunity to participate in the tender for the CDU/VDU Revamp Project at Mumbai Refinery.
This is to confirm that our technical proposal and supporting documents have been submitted in accordance with the tender requirements within the stipulated submission timeline.
We trust that our proposal demonstrates our technical capability, refinery project experience, and commitment toward safe and timely project execution. We remain available for any further clarifications, technical discussions, or presentations required during the evaluation process.
We look forward to the opportunity of working with Indian Oil Corporation Limited on this prestigious project.
Thanking you.
Yours faithfully,
For ABC Engineering & Projects Pvt. Ltd.
Business Development & Proposals Department
By purchasing this prompt, you agree to our terms of service
GPT-5.5
Write professional EPC tender sections and proposals in minutes. Covers: Scope of Work, Technical Compliance Matrix, Method Statement, Project Execution Plan, Commercial Cover Letter and more. Choose your project type, document type and tone. Each run gives a complete formatted document plus scope gap analysis, compliance checklist, winning edge tip and client follow-up email. Works for oil & gas, chemical, power and infrastructure projects.
...more
Added over 1 month ago
